Labor Day News Dump: FERC Hands Enbridge Permit for Tar Sands by Rail Facility

On the Friday before Labor Day — in the form of an age-old “Friday News Dump“ — the Federal Energy Regulatory Commission (FERC) handed a permit to Enbridge, the tar sands-carrying corporate pipeline giant, to open a tar sands-by-rail facility in Flanagan, Ill. by early-2016. 

With the capacity to accept 140,000 barrels of tar sands product per day, the company's rail facility serves as another step in the direction towards Enbridge's quiet creation of a “Keystone XL Clone.” That is, like TransCanada's Keystone Pipeline System sets out to do, sending Alberta's tar sands all the way down to the Gulf of Mexico's refinery row — and perhaps to the global export market.

Flanagan sits as the starting point of Enbridge's Flanagan South pipeline, which will take tar sands diluted bitumen (“dilbit”) from Flanagan to Cushing, Okla. beginning in October, according to a recent company earnings call. From there, Enbridge's Seaway Twin pipeline will bring dilbit to Port Arthur, Texas near the Gulf.

Enbridge made the prospect of a tar sands-by-rail terminal public for the first time during its quarter two investor call.

“In terms of the rail facility, one of the things we're looking at is – and the rail facility is really in relation to the situation in western Canada where there is growing crude oil volumes and not enough pipeline capacity to get it out of Alberta for a two or three year period,” Guy Jarvis, president of liquids pipelines for Enbridge, said on the call.

“So, one of the things we're looking at doing is constructing a rail unloading facility that would allow western Canadian crudes to go by rail to Flanagan, be offloaded, and then flow down the Flanagan South pipeline further into Seaway and to the Gulf.”

FERC has given Enbridge the permit it needs to make that happen.

Wed, 2014-08-27 13:10Steve Horn
Steve Horn's picture

State Dept. Overseers of Contentious Enbridge Tar Sands Pipeline Workaround Have Industry, Torture Ties

The Sierra Club, National Wildlife Federation (NWF) and other green groups recently revealed that pipeline giant Enbridge got U.S. State Department permission in response to its request to construct a U.S.-Canada border-crossing tar sands pipeline without earning an obligatory Presidential Permit.

Enbridge originally applied to the Obama State Department to expand capacity of its Alberta Clipper (now Line 67) pipeline in November 2012, but decided to avoid a “Keystone XL, take two” — or a years-long permitting battle — by creating a complex alternative to move nearly the same amount of diluted bitumen (“dilbit”) across the border.

The move coincides with the upcoming opening for business of Enbridge's “Keystone XL” clone: the combination of the Alberta Clipper expansion (and now its alternative) on-ramp originating in Alberta and heading eventually to Flanagan, Ill., the Flanagan South pipeline running from Flanagan, Ill. to Cushing, Okla. and the Cushing, Okla. to Port Arthur, Texas Seaway Twin pipeline.

Together, the three pieces will do what TransCanada's Keystone XL hopes to do: move dilbit from Alberta's tar sands to Port Arthur's refinery row and, in part, the global export market.

Environmental groups have reacted with indignation to the State Department announcement published in the Federal Register on August 18. The public commenting period remains open until September 17.

Jim Murphy, senior counsel for NWF, referred to it as an “illegal scheme,” while a representative from 350.org says Enbridge has learned from the lessons of its corporate compatriot, TransCanada.

“When we blocked Keystone XL, the fossil fuel industry learned that they have a much stronger hand to play in back rooms than on the streets,” said Jason Kowalski, policy director for 350.org. “They will break the law and wreck our climate if that's what it takes for them to make a buck.”

But as the old adage goes, it takes two to tango. 

That is, influential State Department employees helped Enbridge find a way to smuggle an additional 350,000 barrels of tar sands per day across the border without public hearings or an environmental review. 

Tue, 2014-08-19 15:40Steve Horn
Steve Horn's picture

Court: Key Environmental Law Doesn't Apply to Part of Enbridge Keystone XL "Clone"

Keystone XL Clone Flanagan South

A U.S. District Court for the District of Columbia has ruled that Enbridge’s 600-mile-long Flanagan South Pipeline, a Keystone XL “clone,” is legally cleared to proceed opening for business in October

Approved by the U.S. Army Corps of Engineers via a controversial regulatory mechanism called Nationwide Permit 12 (NWP 12), Judge Kentanji Brown Jackson, an Obama-appointed judge, ruled NWP 12 was not a federal government “action.” Thus, Brown posited that Enbridge did not need to use the National Environmental Policy Act (NEPA) regulatory process and NWP 12 was up to snuff.

The case pitted the Sierra Club and the National Wildlife Federation (NWF) against the Army Corps of Engineers and Enbridge and has lasted for just over a year, with the initial complaint filed on August 13, 2013 (Case #: 1:13-cv-01239-KBJ). 

Sierra Club and NWF submitted the recent precedent-setting Delaware Riverkeeper v. Federal Energy Regulatory Commission (FERC) case as supplemental authority for Sierra Club v. U.S. Army Corps of Engineers on the day that decision was handed down. 

But Jackson brushed it aside, saying it doesn't apply to Flanagan South, despite the fact that the Delaware Riverkeeper v. FERC decision said that a continuous pipeline project cannot be segmented into multiple parts to avoid a comprehensive NEPA review.

Although Enbridge will operate this project as a single pipeline, Flanagan South was broken up into thousands of “single and complete” projects by the Army Corps of Engineers. This helped Enbridge skirt the requirement of a more comprehensive and public-facing NEPA review, which involves public hearings and a public comment period.

“Here, not only was there no NEPA analysis of this massive project, there was never any public notice or opportunity for involvement before it was constructed across four states,” Sierra Club attorney for the case, Doug Hayes, told DeSmogBlog. “The entire thing was permitted behind closed doors.”

For all intents and purposes, then, Flanagan South is a fait accompli and tar sands diluted bitumen (“dilbit”) will begin pumping through it as summer turns to fall. 

Fri, 2013-11-22 12:37Steve Horn
Steve Horn's picture

US Court Denies Halt on Pipeline Set to Replace Keystone XL Northern Half

Flanagan south, keystone xl pipeline

The ever-wise Yogi Berra once quipped “It's like déjà vu all over again,” a truism applicable to a recent huge decision handed down by the United States District Court for the District of Columbia. 

A story covered only by McClatchy News' Michael Doyle, Judge Ketanji Brown Jackson shot down Sierra Club and National Wildlife Federation's (NWF) request for an immediate injunction in constructing Enbridge's Flanagan South tar sands pipeline in a 60-page ruling.

That 600-mile long, 600,000 barrels per day proposed line runs from Flanagan, Illinois - located in the north central part of the state - down to Cushing, Oklahoma, dubbed the “pipeline crossroads of the world.” The proposed 694-mile, 700,000 barrels per day proposed Transcanada Keystone XL northern half also runs to Cushing from Alberta, Canada and requires U.S. State Department approval, along with President Barack Obama's approval. 

Because Flanagan South is not a border-crossing line, it doesn't require the State Department or Obama's approval. If Keystone XL's northern half's permit is denied, Flanagan South - along with Enbridge's proposal to expand its Alberta Clipper pipeline, approved by Obama's State Department during Congress' recess in August 2009 - would make up that half of the pipeline's capacity and then some. 