Presidential Permit

As Dakota Access Protests Escalated, Obama Admin OK’d Same Company for Two Pipelines to Mexico

Left, Mexico's President Enrique Peña Nieto and right, U.S. President Barack Obama

On September 9, the Obama administration revoked authorization for construction of the Dakota Access Pipeline (DAPL) on federally controlled lands and asked the pipeline's owners, led by Energy Transfer Partners, to voluntarily halt construction on adjacent areas at the center of protests by Native Americans and supporters.

However, at the same time the pipeline and protests surrounding it were galvanizing an international swell of solidarity with the Standing Rock Sioux Tribe and its Sacred Stone Camp, another federal move on two key pipelines has flown under the radar.

In May, the federal government quietly approved permits for two Texas pipelines — the Trans-Pecos and Comanche Trail Pipelines — also owned by Energy Transfer Partners. This action and related moves will ensure that U.S. fracked gas will be flooding the energy grid in Mexico.

Appeals Court Rules Keystone XL South Approval Was Legal, Lifting Cloud Over TransCanada

In a 3-0 vote, the U.S. Appeals Court for the Tenth Circuit has ruled that the southern leg of TransCanada's Keystone XL pipeline was permitted in a lawful manner by the U.S. Army Corps of Engineers. 

Keystone XL South was approved via a controversial Army Corps Nationwide Permit 12 and an accompanying March 2012 Executive Order from President Barack Obama. The pipeline, open for business since January 2014, will now carry tar sands crude from Cushing, Oklahoma to Port Arthur, Texas without the cloud of the legal challenge hanging over its head since 2012.

Emails: How State Department Secretly Approved Expanding Piece of Enbridge's "Keystone XL Clone"

State Department Enbridge Emails

DeSmogBlog has obtained dozens of emails that lend an inside view of how the U.S. State Department secretly handed Enbridge a permit to expand the capacity of its U.S.-Canada border-crossing Alberta Clipper pipeline, which carries tar sands diluted bitumen (“dilbit”) from Alberta to midwest markets. 

The State Department submitted the emails into the record in the ongoing case filed against the Department by the Sierra Club and other environmental groups in the U.S. District Court for the District of Minnesota. Collectively, the emails show that upper-level State Department officials hastened the review process on behalf of Enbridge for its proposed Alberta Clipper expansion plan, now rebranded Line 67, and did not inform the public about it until it published its final approval decision in the Federal Register in August 2014.

According to a March 17, 2014 memo initially marked “confidential,” Enbridge's legal counsel at Steptoe & Johnson, David Coburn, began regular communications with the State Department on what the environmental groups have dubbed an “illegal scheme” beginning in at least January 2014. 

Enbridge State Department Emails
Image Credit: U.S. District Court for the District of Minnesota

Environmental groups have coined the approval process an “illegal scheme” because the State Department allowed Enbridge to usurp the conventional presidential permit process for cross-border pipelines, as well as the standard National Environmental Policy Act (NEPA) process, which allows for public comments and public hearings of the sort seen for TransCanada's Keystone XL pipeline.

Further, the scheme is a complex one involving Enbridge's choice to add pressure pump stations on both sides of the border to two pipelines, Enbridge Line 3 and Enbridge Line 67, to avoid fitting under the legal umbrella of a “cross-border” pipeline.

Hastening the approval process — and thus dodging both the conventional presidential permit and NEPA process — came up in a June 6, 2014 memo written by Coburn and his Steptoe co-counsel Josh Runyan. Enbridge's legal argument centered around ensuring profits for its customers “consistent with its obligations as a common carrier.”

State Department Enbridge Emails
Image Credit: U.S. District Court for the District of Minnesota